| February 29, 2008 |
Public information newsletter that will provide full background information on the project to date and summary of public comments |
| March 13, 2008 |
Parks & Recreation Commission information presentation by First Tee and consultants |
| April 2, 2008 |
University Area Community Council Presentation |
| April 3, 2008 |
Scenic Foothills Community Council Presentation |
|
April 15, 2008
|
Public Meeting- 6:30 PM Lidia Selkregg Chalet at Russian Jack Springs Park |
| April 17, 2008 |
Airport Heights Community Council Presentation |
| May 12, 2008 |
Rogers Park Community Council Presentation |
| May 14, 2008 |
Russian Jack Community Council Presentation |
| May 15, 2008 |
Northeast Community Council Presentation |
| May 21, 2008 |
Public Workshop- 6:30PM Lidia Selkregg Chalet at Russian Jack Springs Park |
| Summer 2008 |
Design resolution of public comments (there will be no major new construction this summer). Safety repairs and upgrades to existing facilities to be determined. |
| September 2008 |
Public Meeting |
| Fall/Winter 2008 |
Parks and Recreation Commission and other Municipal Boards/Commissions |
| Spring 2009 |
Phase One construction (based on public input and final design reviews by Park Commission and other Municipal Boards) |
| Ongoing |
Project Fundraising |