Anchorage Parks and Recreation

Chester Creek Phase 2

Phase 2: 2015:

We have identified the highest priorities of concern by segment, spur and hazard. "Phase 2" is scheduled to be completed in summer 2015. Listed below is the project scope as of April 15, 2015.  

1. Phase 2 construction will include 3.5 miles of the main trail corridor from Arctic Blvd. tunnel to Nichols St . Trail Spurs to be repaired are listed below. The project scope of work will be completed in two segments:  

Segment 1: Eagle St. to Nichols St. will begin approximately May 21st and go until July 31st**. 

Segment 2: Arctic Blvd to Eagle St. will begin about July 31st** to Sept. 15th** (or as late Oct. 31, depending on how construction goes). 

Note: schedules subject to change depending on progress and weather.

2. Trail spurs that connect the main trail corridor to adjacent neighborhoods will be repaired based on level of priority and funding. In 2015 we will repair the following spurs and anticipate repairing the remaining trail spurs with residual funding in 2016.

2015 Spur repairs include:

  1. Arc Spur (Arc of Anchorage Trails)
  2. Nichols St. Spur
  3. Maplewood St. Spur
  4. A St. Spur
  5. E. 20th Ave. Spur (Adjacent to Eastchester Creek Park)
  6. E. 24th Ave. Spur
  7. Eagle St. Spur
  8. E St. Spur
  9. C St. Spur

2016 Spurs to be repaired (if funding is avail.):

  1. E. 20th Ave. Spur (Near Tikishla Park)
  2. Tikishla Spur
  3. Sunrise Park Spur
  4. Loussac Place Spur Sports Complex Spur
  5. 23rd Ave. Spur