How Can We Help You?


 Construction Underway on Landfill Methane Gas Project 

  

10/26/2011 | Contact: Sarah Erkmann 343-7103
Mayor's Office

ANCHORAGE- The Municipality of Anchorage Solid Waste Services (SWS) Department and Doyon Utilities, LLC are moving ahead with construction of an energy project at the Anchorage Regional Landfill. 

 

Doyon broke ground for the new Joint Base Elmendorf Richardson (JBER) power plant in June, and currently is constructing the gas pipeline at the landfill.  Doyon hopes to have all underground utilities and foundation work completed by early November, with construction and installation of equipment continuing throughout the winter. 

 

The project is anticipated to be available for commissioning and startup by May 2012, with full commercial production scheduled for January 2013.  Revenues generated by the project will be used to offset rising operating and development costs at the landfill.

 

The project will utilize methane gas, a byproduct of the waste decomposition, to produce electric power.  Solid Waste Services currently collects and flares off this landfill gas to meet federal Clean Air Act requirements.  The project will divert the gas from the existing flare to a scrubber facility located at the landfill. 

The processed gas will then be piped to a power generating plant located on JBER.  The power plant is designed to be able to use both landfill gas and commercial natural gas purchased from ENSTAR.  The facility will provide approximately 23 percent of the general operating demand and can support all emergency power needs of JBER. 

The anticipated cost of the project is approximately $26 million, which is being paid for by Doyon Utilities with some grant funding from the Alaska Energy Authority.

Once complete, the JBER power plant will be the first of its kind in Alaska. The number of landfill gas projects nationally has grown from 399 in 2005 to 519 in 2009, according to the Environmental Protection Agency.